Adding a basement bathroom, replacing a sewer pipe, installing an interior French drain or a backwater valve: in all these cases, the concrete floor must be opened. Here's exactly how it goes, with photos from one of our real job sites.

Projects that require opening the slab

How the job site goes, step by step

1. Layout

We locate existing pipes and mark the cut lines. Precision matters: the less we open, the cheaper it is to close back up.

2. Diamond cutting

The flat saw cuts two straight parallel lines in the slab — usually 4" thick, sometimes more with rebar. Wet cutting: no dust in the house.

Layout and cutting of a trench in a basement slab

3. Breaking and excavation

We break the concrete strip between the cuts, remove the gravel underneath, and the trench is ready for the plumber.

4. Plumbing

The plumber installs the pipes — drains, sewer, water supply. On our job site below, it was a connection to city services.

Plumbing pipes installed in the trench

5. Closing back up

Compacted gravel, then a new concrete pour to level. After a few days of curing, the floor is as good as new — ready for tile, vinyl or epoxy.

How much does it cost?

$400 – $900

For cutting and opening a typical basement trench (plumbing and closing are billed separately). A full perimeter trench for a French drain: often $1,500 to $3,000 of cutting depending on house size.

Mistakes to avoid

Have a basement plumbing project? See our slab sawing service →

Need a quote?

Free, no obligation. Answer within 24h — Ottawa & Gatineau.

Free quote →